[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261484":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261484,844,1,"单选题","根据工程量清单计价规则，非建设单位所为，4小时以内的临时停水停电费应包含在（ ）以内。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","措施项目费",false,{"key":16,"text":17,"correct":14},"B","其他项目费",{"key":19,"text":20,"correct":21},"C","企业管理费",true,{"key":23,"text":24,"correct":14},"D","预留金","根据工程量清单计价规则，非建设单位所为，4小时以内的临时停水停电费应包含在企业管理费以内。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]