[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261475":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261475,844,1,"单选题","和横道图相比较，网络计划的缺点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不能反映工作问题的逻辑",false,{"key":16,"text":17,"correct":14},"B","不能反映出关键工作",{"key":19,"text":20,"correct":21},"C","计算资源消耗量不便",true,{"key":23,"text":24,"correct":14},"D","不能实现电算化","网络计划和横道图相比较，其特有：工序（工作）之间的逻辑关系可以设法表达，但不易表达清楚;适用于手工编制计划;没有通过严谨的进度计划时间参数计算，不能确定计划的关键工作、关键线路与时差;计划调整只能用手工方式进行，其工作量较大;难以适应大的进度计划系统。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]