[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261473":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261473,844,2,"多选题","在施工进度计划的调整中，压缩关键工作持续时间的技术措施有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","增加劳动力",false,{"key":16,"text":17,"correct":14},"B","增加施工机械数量",{"key":19,"text":20,"correct":21},"C","改进施工技术和工艺",true,{"key":23,"text":24,"correct":14},"D","采用工程分包方式",{"key":26,"text":27,"correct":21},"E","采用先进的施工机械","CE","在施工进度计划的调整中，压缩关键工作持续时间的技术措施有改进施工技术和工艺和采用先进的施工机械。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]