[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261472":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261472,844,2,"多选题","在编制施工进度计划的初始方案后，对施工进度计划进行检查的依据有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同规定",true,{"key":16,"text":17,"correct":14},"B","经济效益",{"key":19,"text":20,"correct":21},"C","班组人数",false,{"key":23,"text":24,"correct":14},"D","施工条件",{"key":26,"text":27,"correct":21},"E","资金状况","ABD","在编制施工进度计划的初始方案后，对施工进度计划进行检查的依据有合同规定、经济效益和施工条件。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]