[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261471":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261471,844,2,"多选题","下列选项中，属于在工程网络计划中进行资源优化目的的有（",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资源强度最低",false,{"key":16,"text":17,"correct":18},"B","总费用最低",true,{"key":20,"text":21,"correct":18},"C","资源需用量尽可能低",{"key":23,"text":24,"correct":14},"D","资源需用量最少",{"key":26,"text":27,"correct":18},"E","计算工期满足要求工期","BCE","在工程网络计划中进行资源优化目的是实现总费用最低、资源需用量尽可能低和计算工期满足要求工期",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]