[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261469":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261469,844,2,"多选题","在建筑装饰工程施工过程中，加快施工进度的组织措施有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用先进的施工方法以减少施工过程的数量",false,{"key":16,"text":17,"correct":18},"B","增加工作面，组织更多的专业工作队",true,{"key":20,"text":21,"correct":14},"C","改善劳动条件和外部配合条件",{"key":23,"text":24,"correct":18},"D","增加劳动力和施工机械的数量",{"key":26,"text":27,"correct":14},"E","改进施工工艺","BD","在建筑装饰工程施工过程中，加快施工进度的组织措施有增加工作面，组织更多的专业工作队和增加劳动力和施工机械的数量。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]