[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261466":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261466,844,1,"单选题","下列关于工期的说法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","任何工程都有规定工期、计划工期和计算工期",false,{"key":16,"text":17,"correct":14},"B","计划工期可以小于规定工期",{"key":19,"text":20,"correct":14},"C","计划工期可以等于规定工期",{"key":22,"text":23,"correct":24},"D","计划工期有时可等于计算工期",true,"任何工程都有规定工期、计划工期和计算工期；计划工期可以小于规定工期；计划工期可以等于规定工期",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]