[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261462":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261462,844,2,"多选题","网络计划时间参数的计算方法包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","分析计算法",true,{"key":16,"text":17,"correct":14},"B","图上计算法",{"key":19,"text":20,"correct":14},"C","矩阵计算法",{"key":22,"text":23,"correct":24},"D","时钟测时法",false,{"key":26,"text":27,"correct":14},"E","电算计算法","ABCE","网络计划时间参数的计算方法：分析计算法、图上计算法、矩阵计算法和电算计算法",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]