[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261456":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1261456,844,3,"判断题","构配件配置计划是根据施工预算、施工方案施工进度计划和机械台班定额编制的。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"资源配置计划包括：劳动力配置计划、主要材料配置计划、施工机具配置计划、构配件配置计划",{"id":6,"name":21,"category":22,"favorite":23},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]