[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261450,844,1,"单选题","双代号网络图的三要素是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","节点、箭杆、工作作业时间",false,{"key":16,"text":17,"correct":14},"B","紧前工作、紧后工作、关键线路",{"key":19,"text":20,"correct":21},"C","工作、节点、线路",true,{"key":23,"text":24,"correct":14},"D","工期、关键线路、非关键线路","双代号网络图的三要素是工作、节点、线路",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]