[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261449":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261449,844,1,"单选题","某礼堂在图纸上位于H~K轴及6~9轴之间。该礼堂现进行地面找平层施工前进行基层检查发现混凝土表面有0.2mm左右的裂缝，经分析研究后认为该裂缝不影响结构的安全和使用功能。地面找平层施工工艺步骤如下：材料准备一基层清理→测量与标高控制→铺找平层→刷素水泥浆结合层→养护→验收。试回答以下问题： 找平层施工步骤错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料准备→基层清理",false,{"key":16,"text":17,"correct":14},"B","基层清理→测量与标高控制",{"key":19,"text":20,"correct":21},"C","铺找平层→刷素水泥浆结合层",true,{"key":23,"text":24,"correct":14},"D","养护→验收","找平层施工步骤基层清理→冲洗干净→弹水平控制线→贴灰饼→做冲筋→刷素水泥浆一道→抹找平层砂浆→原浆压光→拉毛（扫粗）→养护8天→质量检查→产品保护",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]