[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1261444,844,1,"单选题","进度计划中各项工作在某一单位时间内所需某种资源数量之和称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资源强度",false,{"key":16,"text":17,"correct":18},"B","资源需用量",true,{"key":20,"text":21,"correct":14},"C","资源限量",{"key":23,"text":24,"correct":14},"D","资源饱和度","进度计划中各项工作在某一单位时间内所需某种资源数量之和称为资源需用量。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]