[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261438":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261438,844,1,"单选题","组织流水施工时，流水步距是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","第一个专业队与其他专业队开始施工的最小间隔时间",false,{"key":16,"text":17,"correct":14},"B","第一个专业队与最后一个专业队开始施工的最小间隔时间",{"key":19,"text":20,"correct":21},"C","相邻专业队相继开始施工的最小间隔时间",true,{"key":23,"text":24,"correct":14},"D","相邻专业队相继开始施工的最大时间间隔","流水步距是指在组织流水施工时，相邻各专业工作队在保证施工顺序、满足连续施工、最大限度搭接和保证工程质量要求的条件下，相继投入施工的最小时间的间隔。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]