[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261436":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261436,844,2,"多选题","下列关于室内装饰装修工程施工顺序基本原则的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先湿作业，后干作业",true,{"key":16,"text":17,"correct":18},"B","先干作业，后湿作业",false,{"key":20,"text":21,"correct":14},"C","先管线、后饰面",{"key":23,"text":24,"correct":18},"D","先饰面、后管线",{"key":26,"text":27,"correct":14},"E","先墙顶、后地面","ACE","室内装饰装修工程施工顺序基本原则：先湿作业，后干作业；先管线、后饰面；先墙顶、后地面",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]