[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261424":3},{"question":4,"library":19},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":9},1261424,844,3,"判断题","各施工段的劳动量应尽量相等，以保证各施工过程连续施工、均衡施工。若不相同时，应将先施工的施工段划得大一些，以免从第二个施工过程开始产生“阻塞”。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,{"id":6,"name":20,"category":21,"favorite":22},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]