[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261419":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261419,844,1,"单选题","某分项工程的工程量为1000m3，该分项工程的人工时间定额为0.1工日\u002Fm3，计划每天安排两班人施工，每班5人，则其持续时间为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","100",false,{"key":16,"text":17,"correct":14},"B","50",{"key":19,"text":20,"correct":14},"C","40",{"key":22,"text":23,"correct":24},"D","10",true,"1000\u002F（1\u002F0.1*5*2）=10d",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]