[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261417":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261417,844,1,"单选题","下列关于施工段的划分要求，说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工段的分界同施工对象的结构界限尽量一致",false,{"key":16,"text":17,"correct":14},"B","各施工段上所消耗的劳动量尽量相近",{"key":19,"text":20,"correct":14},"C","要有足够的工作面",{"key":22,"text":23,"correct":24},"D","分层又分段时，每层施工段数应少于施工过程数",true,"施工段的划分要求有：施工段的分界同施工对象的结构界限尽量一致；各施工段上所消耗的劳动量尽量相近；要有足够的工作面",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]