[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261415,844,1,"单选题","某室内装饰工程项目部关于施工顺序的安排，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风管安装→墙面涂饰→吊顶安装→地面铺贴",false,{"key":16,"text":17,"correct":14},"B","吊顶安装→风管安装→墙面涂饰→地面铺贴",{"key":19,"text":20,"correct":21},"C","风管安装→吊顶安装→地面铺贴→墙面涂饰",true,{"key":23,"text":24,"correct":14},"D","地面铺贴→吊顶安装→风管安装→墙面涂饰","室内装饰工程项目部关于施工顺序的安排应遵循上下左右、前后内外，风管安装→吊顶安装→地面铺贴→墙面涂饰",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]