[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261414":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261414,844,1,"单选题","某工程地面浇筑混凝土找平层所需劳动量为1200个工日，可分为劳动量相等的3个施工段组织流水施工，每天采用两班制，每段投入的人工数为40个工日，其流水节拍值为（ ）d。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":14},"C","8",{"key":22,"text":23,"correct":24},"D","5",true,"1200\u002F（2*3*40）=5d",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]