[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261380":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261380,844,1,"单选题","下列窗帘盒施工流程，正确的顺序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料准备→安装木基层→窗帘盒安装→定位放线一窗帘轨固定一验收",false,{"key":16,"text":17,"correct":14},"B","材料准备一安装木基层一定位放线一窗帘盒安装一窗帘轨固定一验收",{"key":19,"text":20,"correct":21},"C","材料准备→定位放线→安装木基层→窗帘盒安装→窗帘轨固定一验收",true,{"key":23,"text":24,"correct":14},"D","材料准备→定位放线一安装木基层一窗帘轨固定一窗帘盒安装一验收","窗帘盒施工流程：材料准备→定位放线→安装木基层→窗帘盒安装→窗帘轨固定一验收",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]