[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261276":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1261276,844,3,"判断题","脚手架专项施工方案中，单、双排脚手架拆除作业必须由上而下逐层进行，严禁上下同时作业，可以先将连墙件整层或数层拆除后再拆除脚手架。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"在脚手架使用期间，严禁拆除主节点处的纵、横向水平杆，纵、横向扫地杆、连墙件。",{"id":6,"name":21,"category":22,"favorite":23},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]