[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261269":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261269,844,2,"多选题","下列选项中，属于施工现场临时用电组织设计的内容的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","负荷计算",true,{"key":16,"text":17,"correct":14},"B","设计配电系统",{"key":19,"text":20,"correct":14},"C","设置防雷装置",{"key":22,"text":23,"correct":24},"D","设置垂直运输通道",false,{"key":26,"text":27,"correct":14},"E","选择变压器","ABCE","施工现场临时用电组织设计的内容包括：负荷计算、设计配电系统、设置防雷装置、选择变压器等。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]