[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261185":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261185,844,1,"单选题","施工成本控制的工作内容之一是计算和分析（ ）之间的差异。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预测成本与实际成本",false,{"key":16,"text":17,"correct":14},"B","预算成本与计划成本",{"key":19,"text":20,"correct":21},"C","计划成本与实际成本",true,{"key":23,"text":24,"correct":14},"D","预算成本与实际成本","通过随时揭示并及时反馈，严格审查各项费用是否符合标准，计算实际成本和计划成本之间的差异并进行分析。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]