[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261182":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261182,844,2,"多选题","项目成本控制的重心应放在项目经理部，控制环节包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","计划预控",true,{"key":16,"text":17,"correct":14},"B","过程预控",{"key":19,"text":20,"correct":14},"C","纠偏预控",{"key":22,"text":23,"correct":24},"D","投标预控",false,{"key":26,"text":27,"correct":24},"E","竣工审计","ABC","项目成本控制的重心应放在项目经理部，控制环节包括计划预控、过程预控、纠偏预控等。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]