[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261180":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261180,844,2,"多选题","施工成本控制可分为（ ）等控制内容和工作。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","程序控制",false,{"key":16,"text":17,"correct":18},"B","事先控制",true,{"key":20,"text":21,"correct":18},"C","过程控制",{"key":23,"text":24,"correct":18},"D","事后控制",{"key":26,"text":27,"correct":14},"E","全员控制","BCD","施工成本控制可分为事先控制、事中控制、事后控制等控制内容和工作。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]