[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261179":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1261179,844,1,"单选题","施工成本预测的实质是在施工项目的施工之前（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对成本因素进行分析",false,{"key":16,"text":17,"correct":18},"B","分析可能的影响程度",true,{"key":20,"text":21,"correct":14},"C","估算计划与实际成本之间的可能差异",{"key":23,"text":24,"correct":14},"D","对成本进行估算","预测这些因素对工程成本中有关项目（成本项目）的影响程度，预测出工程的单位成本或总成本。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]