[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261165":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261165,844,2,"多选题","施工成本控制的依据包括：（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程量变更",true,{"key":16,"text":17,"correct":14},"B","工程承包合同",{"key":19,"text":20,"correct":21},"C","工程竣工期限",false,{"key":23,"text":24,"correct":14},"D","进度报告",{"key":26,"text":27,"correct":14},"E","工程变更","ABDE","施工成本控制的依据包括：（1）工程量变更；（2）工程承包合同；（3）进度报告；（4）工程变更。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]