[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261164":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1261164,844,1,"单选题","某项目进行成本偏差分析，结果为：已完工作预算成本（BCWP）—已完工作实际成本（ACWP）0。则说明（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本超支，进度提前",true,{"key":16,"text":17,"correct":18},"B","成本节约，进度提前",false,{"key":20,"text":21,"correct":18},"C","成本超支，进度拖后",{"key":23,"text":24,"correct":18},"D","成本节约，进度拖后","当CV为负值时，即表示项目运行超出预算成本。当SV为正值时，表示进度提前，即实际进度快于计划进度。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]