[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1261152,844,1,"单选题","SV＝BCWP—ACWP，由于两项参数均以预算值（计划值）作为计算基准，所以两项参数之差，反映项目进展的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用偏差",false,{"key":16,"text":17,"correct":18},"B","进度偏差",true,{"key":20,"text":21,"correct":14},"C","费用绝对偏差",{"key":23,"text":24,"correct":14},"D","进度相对偏差","SV＝BCWP—ACWP，由于两项参数均以预算值（计划值）作为计算基准，所以两项参数之差，反映项目进展的进度偏差。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]