[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261147":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261147,844,2,"多选题","有效控制建设工程造价的组织措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","重视工程设计多方案的选择",false,{"key":16,"text":17,"correct":18},"B","明确工程造价管理职能分工",true,{"key":20,"text":21,"correct":14},"C","严格审查施工组织设计",{"key":23,"text":24,"correct":14},"D","采取对节约投资有利的奖励措施",{"key":26,"text":27,"correct":18},"E","明确造价控制者及其任务","BE","组织措施包括明确工程造价管理职能分工、明确造价控制者及其任务。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]