[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261144":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261144,844,2,"多选题","施工成本控制需按（ ）进行有效控制。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","事先控制",true,{"key":16,"text":17,"correct":14},"B","事中控制",{"key":19,"text":20,"correct":14},"C","事后控制",{"key":22,"text":23,"correct":24},"D","全面控制",false,{"key":26,"text":27,"correct":24},"E","全员控制","ABC","施工成本控制可分为事先控制、事中控制和事后控制。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]