[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261143":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261143,844,2,"多选题","施工成本管理的任务和环节主要包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工成本计划",true,{"key":16,"text":17,"correct":18},"B","施工成本经营",false,{"key":20,"text":21,"correct":14},"C","施工成本控制",{"key":23,"text":24,"correct":14},"D","施工成本核算",{"key":26,"text":27,"correct":14},"E","施工成本分析与考核","ACDE","施工成本管理的环节和任务主要包括：1）施工成本预测；2）施工成本计划；3）施工成本控制；4）施工成本核算；5）施工成本分析；6）施工成本考核。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]