[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261136":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261136,844,2,"多选题","施工成本计划应满足的要求有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","合同规定的项目质量和工期要求。",true,{"key":16,"text":17,"correct":14},"B","组织对项目成本管理目标的要求。",{"key":19,"text":20,"correct":14},"C","以经济合理的项目实施方案为基础的要求。",{"key":22,"text":23,"correct":14},"D","有关定额及市场价格的要求。",{"key":25,"text":26,"correct":27},"E","高于社会平均收益率",false,"ABCD","施工成本计划应满足的要求：1）合同规定的项目质量和工期要求；2）组织对项目成本管理目标的要求；3）以经济合理的项目实施方案为基础的要求；4）有关定额及市场价格的要求；5）类似项目提供的启示。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]