[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261135":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261135,844,2,"多选题","工程变更包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工程量变更",true,{"key":16,"text":17,"correct":14},"B","工程项目变更",{"key":19,"text":20,"correct":14},"C","进度计划的变更",{"key":22,"text":23,"correct":14},"D","施工条件的变更",{"key":25,"text":26,"correct":27},"E","预算定额的变更",false,"ABCD","工程变更一般包括：设计变更、进度计划变更、施工条件变更、技术规范与标准变更、施工次序变更、工程量变更等。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]