[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1261117,844,1,"单选题","施工项目成本控制工作从施工项目（ ）开始直到竣工验收，贯穿于全过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计阶段",false,{"key":16,"text":17,"correct":18},"B","投标阶段",true,{"key":20,"text":21,"correct":14},"C","施工准备阶段",{"key":23,"text":24,"correct":14},"D","正式开工","施工项目成本控制工作从施工项目投标阶段开始直到竣工验收，贯穿于全过程。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]