[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1261113,844,1,"单选题","施工项目目标成本的确定，人工、材料、机械的价格（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按市场价取定",false,{"key":16,"text":17,"correct":14},"B","按投标报价文件规定取定",{"key":19,"text":20,"correct":14},"C","按现行机械台班单价、周转设备租赁单价取定",{"key":22,"text":23,"correct":24},"D","按实际发生价取定",true,"施工项目目标成本的确定，人工、材料、机械的价格按实际发生价取定。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]