[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261111":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1261111,844,1,"单选题","施工成本计划通常有三类指标,即（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拟定工作预算成本指标,已完成工作预算成本指标和成本降低率指标",false,{"key":16,"text":17,"correct":18},"B","成本计划的数量指标,质量指标和效益指标",true,{"key":20,"text":21,"correct":14},"C","预算成本指标,计划成本指标和实际成本指标",{"key":23,"text":24,"correct":14},"D","人、财、物成本指标","施工成本计划一般情况下有以下三类指标：1）成本计划的数量指标；2）成本计划的质量指标；3）成本计划的效益指标。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]