[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261099":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1261099,844,1,"单选题","在实施施工成本管理的多项措施中，分解施工成本管理目标、进行风险分析和偏差原因分析是施工成本管理的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":21},"C","经济措施",true,{"key":23,"text":24,"correct":14},"D","合同措施","分解施工成本管理目标、进行风险分析和偏差原因分析是施工成本管理的经济措施。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]