[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261070":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1261070,844,1,"单选题","不属于运用动态控制原理控制施工进度的步骤是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工成本目标的逐层分解",false,{"key":16,"text":17,"correct":18},"B","在施工过程中对施工成本目标进行动态跟踪和控制",true,{"key":20,"text":21,"correct":14},"C","如有必要（即发现原定的施工进度目标不合理，或原定的施工进度目标无法实现等），则应调整施工进度目标",{"key":23,"text":24,"correct":14},"D","定期对施工进度的计划值和实际值进行比较","在建筑装饰施工项目的质量控制应当贯彻全面、全员、全过程质量管理的思想，运用动态控制原理，进行质量的事前控制、事中控制和事后控制。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]