[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261050":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261050,844,2,"多选题","属于部门控制式项目组织缺点的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","各类人员来自不同部门，互相不熟悉",false,{"key":16,"text":17,"correct":14},"B","不能适应大型项目管理需要，而真正需要进行施工项目管理的工程正是大型项目",{"key":19,"text":20,"correct":21},"C","不利于对计划体系下的组织体制（固定建制）进行调整",true,{"key":23,"text":24,"correct":21},"D","不利于精简机构",{"key":26,"text":27,"correct":14},"E","具有不同的专业背景，难免配合不力","CD","优点是：1、机动、灵活，可随项目的开发与结束进行组织或解散；2、由于这种结构是根据项目组织的，任务清楚，目的明确，各方面有专长的人都是有备而来。3、它还加强了不同部门之间的配合和信息交流，克服了直线职能结构中各部门互相脱节的现象。4、合理调配资源。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]