[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261036":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},1261036,844,2,"多选题","施工质量控制的基本环节包括（ ）。 A.质量的事前控制 B.质量事中控制 C.质量事后控制 D.施工准备控制E施工过程控制",[11,14,16,18,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":13},"C",{"key":19,"text":19,"correct":20},"D",false,{"key":22,"text":22,"correct":20},"E","ABC","施工质量控制应贯彻全面、全过程质量管理的思想，运用动态控制原理，进行质量的事前控制、事中控制和事后控制。",{"id":6,"name":26,"category":27,"favorite":28},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]