[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261035":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261035,844,2,"多选题","施工阶段项目管理的任务，就是通过施工生产要素的优化配置和动态管理，以实现施工项目的（ ）管理目标。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","质量",true,{"key":16,"text":17,"correct":14},"B","成本",{"key":19,"text":20,"correct":14},"C","进度",{"key":22,"text":23,"correct":14},"D","安全",{"key":25,"text":26,"correct":27},"E","环境",false,"ABCD","施工阶段项目管理的任务，就是通过施工生产要素的优化配置和动态管理，以实现施工项目的质量、成本、进度、安全等管理目标。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]