[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1261016":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1261016,844,2,"多选题","质量控制点应选择那些（ ）的对象进行设置。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","技术要求高",true,{"key":16,"text":17,"correct":14},"B","发生质量问题时危害大",{"key":19,"text":20,"correct":14},"C","工程质量影响大",{"key":22,"text":23,"correct":24},"D","施工工序复杂",false,{"key":26,"text":27,"correct":14},"E","施工难度大","ABCE","质量控制点应选择那些技术要求高、施工难度大、对工程质量影响大或是发生质量问题时危害大的对象进行设置。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]