[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260981":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1260981,844,1,"单选题","调整进度管理的方法和手段，改变施工管理和强化合同管理等属于（ ）的纠偏措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":18},"B","管理措施",true,{"key":20,"text":21,"correct":14},"C","经济措施",{"key":23,"text":24,"correct":14},"D","进度措施","调整进度管理的方法和手段，改变施工管理和强化合同管理等属于管理措施（包括合同措施）的纠偏措施。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]