[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260971":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1260971,844,1,"单选题","不属于项目目标动态控制的纠偏措施是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","管理措施（包括合同措施）",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","处置",true,"项目目标动态控制的纠偏措施包括：组织措施、管理措施（包括合同措施）、经济措施、技术措施。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]