[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1260928,844,1,"单选题","某钢结构安装工程发生整体倾覆事故，正在施工的工人3人死亡，5人重伤。事故发生后，进行了详细的事故调查，对此： 在施工阶段，通过对施工全过程、全面的质量监督管理、协调和决策，保证竣工项目达到投资决策所确定的质量标准，此质量控制目标属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理单位的控制目标",false,{"key":16,"text":17,"correct":18},"B","施工单位的控制目标",true,{"key":20,"text":21,"correct":14},"C","建设单位的控制目标",{"key":23,"text":24,"correct":14},"D","供货单位的控制目标","施工阶段，通过对施工全过程、全面的质量监督管理、协调和决策，保证竣工项目达到投资决策所确定的质量标准，此质量控制目标属于",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]