[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260917":3},{"question":4,"library":19},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":9},1260917,844,3,"判断题","施工进度计划根据施工项目划分的粗细程度可分为指导性施工进度计划和控制性施工进度计划两类。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,{"id":6,"name":20,"category":21,"favorite":22},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]