[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260915":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260915,844,2,"多选题","下列关于实施性进度计划主要作用的说法，正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","确定各分部分项工程的施工时间及其相互之间的衔接",true,{"key":16,"text":17,"correct":14},"B","确定一个月度或旬的机械需求",{"key":19,"text":20,"correct":14},"C","确定一个月度或旬的人工需求",{"key":22,"text":23,"correct":14},"D","确定一个月度或旬的建筑材料需求",{"key":25,"text":26,"correct":27},"E","是施工进度动态控制的依据",false,"ABCD","实施性施工进度计划的主要作用如下：（1）确定施工作业的具体安排；（2）确定（或据此可计算）一个月度或一个阶段的人工需求（工种和相应的数量）；（3）确定（或据此可计算）一个月度或一个阶段的施工机械的需求（机械名称和数量）；（4）确定（或据此可计算）一个月度或一个阶段的建筑材料",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]