[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260913":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1260913,844,2,"多选题","下列选项中，可以调整施工进度计划的方法有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","增加资源的投入",true,{"key":16,"text":17,"correct":14},"B","改变工作的逻辑关系",{"key":19,"text":20,"correct":14},"C","资源供应的调整",{"key":22,"text":23,"correct":14},"D","提高劳动生产率",{"key":25,"text":26,"correct":27},"E","长期延长劳动时间",false,"ABCD","调整施工进度计划的方法包括:增加资源的投入、改变工作的逻辑关系、资源供应的调整、提高劳动生产率等。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]