[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1260910":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1260910,844,1,"单选题","某项目进行墙面进行抹灰、涂饰施工。现由于各种原因，项目年前需要完成施工并交付验收，需要抢工作业。原计划工期如下为，抹灰施工10d，抹灰后间隔10d，涂饰施工12d。项目部原方案为增加抹灰工5人，涂饰工人5人，可使抹灰和涂饰施工时间各减少3d。但考虑到年前抹灰工人工资从原先的200元\u002Fd上涨到了300元\u002Fd，涂饰工人从原先的180元\u002Fd上涨到了250元\u002Fd，故项目部从节省成本考虑，将抹灰后的间隔时间缩短到4d以保证工期顺利完成。试回答以下问题： 当进度无法满足施工要求时，应考虑加快进度的措施，这些措施不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压缩某项工作的合理工期",true,{"key":16,"text":17,"correct":18},"B","增加某项工作的资源投入",false,{"key":20,"text":21,"correct":18},"C","改变工作的先后顺序",{"key":23,"text":24,"correct":18},"D","改变工作的持续时间","调整施工进度计划的方法包括:增加资源的投入、改变工作的逻辑关系、资源供应的调整、提高劳动生产率等。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰施工)专业管理实务 岗位知识","建筑工程",0]